Learn, Share, Apply
A commodity-loaded schedule and a resource-loaded schedule are two different approaches used in project management to plan and track the allocation of resources and the progress of tasks within a project. They serve different purposes and provide distinct insights into the project’s execution. Here’s a breakdown of each: Commodity-Loaded Schedule: A commodity-loaded schedule focuses on…
In the context of project management or business processes, “trend” and “change order” are two distinct terms with different meanings and implications: Trend: A trend refers to a pattern or direction of change over time, indicating a consistent shift in a particular direction. Trends are often identified by analyzing data points or performance metrics over…
Schedule Risk Analysis (SRA) is a technique used to assess and analyze the potential impact of uncertainties and risks on project schedules. Here are some key characteristics of Schedule Risk Analysis: Probabilistic Approach: SRA employs a probabilistic approach by incorporating uncertainties and risks into the project schedule. It considers the likelihood and impact of various…
To update the baseline feature in Primavera P6, follow these steps: Launch Primavera P6 and open the project you want to update the baseline for. Go to the “Projects” tab and select the project from the list. In the top menu, click on the “Project” dropdown and select “Maintain Baselines.” The “Maintain Baselines” dialog box…
Table 3-1Sample Table of Contents for a Schedule Basis Memorandum Section Number Section Title 1.0 INTRODUCTION 2.0 EXECUTIVE SUMMARY 3.0 CURRENT PROJECT STATUS 4.0 BASIS OF SCHEDULE 5.0 RISK ANALYSIS 6.0 SUPPORTING APPENDICES, ATTACHMENTS AND EXHIBITS The detail and depth of discussion for each of the above sections depends on the size and scope of…
Role of Performance Factor in EVM: Performance Factor (PF) plays an important role in forecasting while calculating the value of Estimate to Complete (ETC) in Earned Value Management (EVM). Different values of this Performance Factor will generate a totally different value of ETC, which in turn would help in the calculation of the Estimate at Completion (EAC). In fact, Earned…